Guide · Takeoff method

How to do a quantity takeoff from a PDF on a Mac

A takeoff is only as good as its scale, its naming and its checks. This is the method I use, step by step, from opening the drawing set to handing over a spreadsheet of quantities.

Short answer

Calibrate every sheet to its own scale and verify it against a printed dimension. Name each measurement after the item you will price. Measure areas, then lengths, then counts, deducting openings as you go. Run a check for double counting and unscaled sheets, then export the totals to CSV. On a Mac you can do all of this natively in an app like Project Blueprint, without Windows.

1. Prepare the drawing set

Most takeoff errors start before the first click.

2. Set and verify the scale on every sheet

A scale error multiplies through every quantity on the sheet, and through areas it multiplies twice. A plan measured at 1:100 when it was printed at 1:50 gives areas four times too large.

  1. Calibrate from a long known dimension.In Blueprint, Measure › Calibrate, then click the two ends of the longest dimension you can find, such as an overall building length, and type its value. Longer dimensions reduce click error.
  2. Or set the printed scale.Measure › Set Scale lets you pick the scale from the title block, if you trust that the PDF was exported at true size.
  3. Verify against a second dimension.Measure › Verify Scale: draw along a different dimension line and Blueprint reads the figure beside it. If they disagree, it offers the right scale.

Each sheet keeps its own scale in Blueprint, so calibrating a detail sheet won't change your plans. For scanned sheets that have been stretched, set separate horizontal and vertical scales. The drawing scale guide covers the edge cases.

3. Decide how you'll name and group

Name every measurement after the line it will price against, before you start. In Blueprint, the subject is the name, and the Markups List groups and totals by subject, layer and page.

SubjectToolUnit
Floor finish: carpetAream²
Floor finish: timberAream²
SkirtingPolylengthm
External wallPolylengthm
Slab thickeningVolumem³
Door: single leafCountNo.

Use a different colour per subject. It makes gaps and overlaps obvious at a glance, and it reads well when you hand the marked-up PDF to someone else.

4. Measure in a sensible order

  1. Areas first. Trace each room or zone with the Area tool. Snap to the inside face of walls for finishes, or the centreline if your measurement rules say so.
  2. Lengths next. Walls, skirting, cornice and kerbs with Polylength. Use Perimeter when you need the edge of an area you have already traced.
  3. Volumes. Excavation, fill and concrete with Volume: an area plus a depth. The depth stays true if you later switch between mm and m.
  4. Counts last. Doors, windows and fittings with Count. Blueprint numbers each one as you click, so a skipped item stands out.
Close-up of a takeoff in Project Blueprint: rooms traced as areas in amber, blue, teal and violet by floor finish, each showing its area in square metres, with numbered door and window counts.
Areas coloured by floor finish, with numbered door and window counts. From a fictional 13-room demo house.

5. Deduct openings once, and only once

Use cutouts for voids, stairwells, columns and openings inside an area. In Blueprint, a cutout takes away only what is inside the area, and overlapping cutouts are only taken away once. Note your deduction rule (for example, openings over a stated size) at the top of the takeoff so the next person applies the same one.

6. Check before anything goes out

Run two kinds of check: the automatic one, and a sense check.

227.76 m²floor area
65.52 mexternal wall
11doors
13windows

Totals from the fictional demo house shown above, measured in Blueprint 1.1.2.

7. Export and keep a record

8. Handle revisions without starting again

When a new revision arrives, open both versions and use Document › Overlay Compare to overlay, blink or swipe between them. Re-measure only the clouded or changed areas, and keep the superseded takeoff. Being able to show what changed between revisions is what settles variation claims.

Frequently asked questions

What is a quantity takeoff?

A quantity takeoff is the list of measured quantities taken from construction drawings: areas of flooring, lengths of wall, volumes of concrete, numbers of doors. It is the base for a cost estimate or a bill of quantities.

Can I measure a PDF drawing accurately?

Yes, if the PDF was exported from CAD at a known scale and you calibrate it. Check the scale against at least one printed dimension on every sheet. Scanned or resized PDFs need extra care, and sometimes separate horizontal and vertical scales.

Should I measure net or gross areas?

Follow the measurement rules your estimate is prepared to, such as NZS 4202 in New Zealand or the Australian Standard Method of Measurement. Whichever you use, deduct openings consistently and note the rule in your takeoff so someone else can check it.

How do I take off a revised drawing?

Compare the new revision with the old one first. Overlay or blink the two sheets to see what moved, then re-measure only the changed areas. Keep the old takeoff so you can show what changed and why.

Can I export the quantities to Excel?

Yes. In Project Blueprint, export the Markup Summary as CSV. It opens in Excel with quantities as numbers, ready to price or paste into a bill of quantities.

Sources

Prices and product details were checked on 13 October 2026. They change, so check each vendor's site before you buy.

Put a real drawing set through it.

Try Project Blueprint free for 14 days on your own drawings. No card needed. If it fits your work, the Founder licence is a one-off US$19 for two Macs.

macOS 14 or later · Apple silicon and Intel · Founder licence US$19 for the first 100 customers, then US$79 one-off